Project Details

 

Project Scale:  60 MW
Maximum Number of Turbines:  25

Land

  • Southeast of Greenwich, Ohio
  • 4,600+ acres leased
  • Predominate graze and cropped ground

Wind Assessment

  • (1) 60 meter met mast installed June 2010
  • (2) sodar units on site since May 2011
  • Wind resource supports utility grade power

Project Design, Environmental & Permitting

  • FAA/microwave/communications cleared
  • Wildlife and environmental studies complete
  • Environmental areas of concern and known setback requirements defined; siting of turbines in process
  • Pre-Application filed with OPSB April 2013 (Ohio Power Siting Board)
  • Approval: Opinion, Order and Certificate received from OPSB in August 2014

Grid Connection

  • Interconnection with PJM; currently in Facility Study Phase
  • Small 3 ring bus type substation to be located in project area to connect to grid.
  • Proposed interconnection to 69kV line on site, owned by American Electric Power (AEP)